September 3, 2011

The Bottom is Done!

We've been sandblasting and painting since Wednesday and I'm excited to say that the bottom of the hull is now DONE!! 

Ty and Mark will be starting on the sides tomorrow and will go until they run out of sand. Unfortunately we don't have much left and the new order won't be here until Wednesday.
Sandblasted stern




Ready for paint

Painted
 
Done!
The rain has been pretty much relentless and we now have a lake and black sand beach under the boat. Too bad it's not hot and dry out; that sand would be nice and warm!





Dave has been getting in some time on the forklift this week, hauling pallets of blasting sand.



We purchased a couple of bags of sand from a guy who was blasting in the yard a couple of months ago when we first got there.  Unfortunately one of the bags of sand is really wet and we won't be able to use it.  We were able to find two pallets of sand at Agpro however, they don't deliver.  Luckily our friend Kristan was able to pick up the pallets and deliver them to us at the boat.  A big thank you to Kristan for taking time out of his busy morning to help us!!

Kristan arrives with the blasting sand

Dave getting the sand off the truck

Dave & Kristan

The sandblaster is blowing dust all over the place; the topside of the boat is a mess! There is dust everywhere! I'm so glad we got the house wrapped up before we started this part of the project. 

Topside bow

Topside stern
~Misty~ 

September 2, 2011

Still Sandblasting

We're still sandblasting and painting.  The weather isn't really cooperating with us and we've had some equipment issues, but we're keeping at it. We sandblast for several hours, then paint and come back and do it again the next day. By the end of today we hope to have the rest of the bottom of the hull finished and up the sides to the rub rail. 

I headed down to the boat this morning to check on the paint; it had only been drying for about 6 hours so we weren't sure it would be ok to sandblast yet.  Paint seemed ok, but we discovered that one of the bags of "sand" we bought yesterdy is wet. GREAT!!  That explains the problems we were having last night. The sand has to be completely dry or it plugs up the equipment and is not effective.  Don't know how we're going to get it dry.

No new pics right now... will take more today as we work up the sides of the boat.  Keeping fingers crossed for some drier weather; I want to get this job done!

~Misty~


September 1, 2011

Here's a short video of Mark sandblasting.

~Misty~



We're Sandblasting!

Paul finished applying the final coat of roofing before we started the sandblasting. He added rubber granules so there would be some grip to the roof. This will really help if I'm up there taking pictures!



We finished wrapping the house in cardboard and covered the whole thing in visqueen to protect it.



We got started on the sandblasting yesterday and managed to finish about 1/3 of the bottom of the hull and were able to get a barrier coat of paint on too.  The sandblasting is going a little slower than we expected, in part due to equipment issues we've had.  The filters that draw the water out of the air are old and dirty and should have been replaced months ago.  Unfortunately we can't just run down to the store to buy new ones as no one in Juneau carries anything like that. The person who owns the equipment assures us that he can get filters here quickly, so in the meantime we'll just power through.  Our other issue is that we're in a rainforest and it's raining, so the air is super humid right now. 

Misty all geared up.  Of course I had to quote Darth Vader while wearing the mask

Ty sandblasting

Small section of bow.  Sandblasted on the left, old paint on the right

Ty & Mark

Starboard bow area

Looking underneath


Bow

Looking at the "I" beam, sandblasted
Dave mixing the bottom paint

PAINTING!

Finished paint

~Misty~


August 28, 2011

The Light at the End of the Tunnel...

I can finally see it... the light at the end of the tunnel!  The exterior projects are starting to wind down and we're prepping the SHAD for the much awaited sandblasting and painting.  I've been told that we'll start the sandblasting Wednesday morning at 6am.  I'm excited, nervous and terrified!  More than once I've thought that we've bitten off more, WAY MORE, than we can chew, but we're doing it.  I don't want to get ahead of myself, but I think we're just a couple of weeks from being back in the water!

Here's the front of the house with all of the new beautiful wood.


 Here are some close ups of the wood around the top of the house. 



I can't remember what these are called, but they will be on the roof where the stacks for the oil stove and water heater will come through the roof.


Paul and Dave mixing the roof coating


I prepped the roofs for the silicone roofing.


Paul painting the roofing around the edges.


Wheelhouse roof halfway done.


Lower roof almost done.


First coat DONE!



Part of prepping for the sandblasting is to protect the house.  The last thing we want to do is accidentally sandblast the epoxy off the house or blast the portholes and windows.  We're wrapping the lower parts of the house, windows & portholes with cardboard and draping the rest of the house with visqueen.



~Misty~

August 22, 2011

Welding is DONE!!

Juneau's weather has been less than pleasant over the last several days.  We've had high winds and record rainfall resulting in flooding in the lakes, rivers and small streams.  Unfortunately for us the high winds wreaked havoc on our boat cover.  Dave and I went down Saturday morning to check everything out.  The tarp had come undone in several places, rain was coming in through the top and some of the conduit had come apart.  It was way too windy to get that thing back together, so we rallied the troops for an attempt on Sunday. Thankfully the wind had died down enough for us to get it back together!!  We duct taped, zip tied and screwed the cover back together in a couple of hours.  Sorry... no pictures as I couldn't hang on to the tarp and camera at the same time.

The weather was so crummy  on Sunday that I didn't even take the time to check out all the work the welders had done. They are finished and even took the time to clean up the whole area under the boat.  It was really nice to show up to all of that done as well!

Here are some pictures of the welder's work.

On the stern the exhaust pipes come up from the lazarette and will go through the new roof overhang.  There was some rusting around the bottom of the pipes on both sides, so the welder removed the steel around them and replaced it.


Port side exhaust.

Starboard side exhaust.
 When the SHAD was built in 1958, the anchor winch sat right in front of the house in the middle of the front deck.  The anchor chain would go up through the hause pipe in the bow to the winch.  After much discussion it was decided that we should close the hause pipe.  This will help keep water off the deck, as you'll see in the next picture the pipe comes right up through the bow deck.
Hause pipe at the bow.

This is the other end of the anchor chain hause pipe, right on the bow deck.  It was just big enough to get my size 8.5 foot wedged inside.  I was more concerned about breaking an ankle than getting the deck wet!

Hause pipe on the bow deck.

The rub rail is now on all the way around the hull!


Starboard side.
The generator located in the engine room used to exhaust right at the water line.  Dave had the welder close off the original exhaust hole and move it up a little higher.


Shop floor drain.

Galley sink drain.

Shower & toilet drains.